The new Planning Regulations came into effect on the 11th March
2002
Types of Planning Application
General construction
- Application for Outline Permission
- Application for Permission
- Application for Retention
- Application for Permission following the
Grant of Outline Permission*
Any application can
be rejected by the Local Authority as ‘invalid ‘
* Replaces ‘Approval’.
General Requirements
- Newspaper Notice
- Site Notice
- Completed Application Form
- Appropriate Fee (presently €65 house application,
€34 extension).
- Drawings
- Schedule of Drawings **
- A Section 97 certificate (if appropriate)
** New requirement.
Background Information
- Is the site located in an Architectural Conservation
Area?
- Is the site located in a Strategic Development
Zone?
- Is the site located in the vicinity of an
establishment?
- Is the structure a Protected Structure (or
proposed to be)
Is an EIS, IPC or Waste Licence Required
(IPC = Integrated Pollution Control)
Newspaper Notice – Requirements
- Each Planning Authority must provide a list
of approved newspapers to applicants
- Must be published in the two-week period
immediately preceding the making of the application.
- Townland name or Postal address
- Type of application
- ‘Approval’ option has been abolished and
Outline Reference must be given.
- If within category noted in ‘Background Information’,
this must be stated.**
- That the application can be Inspected or
Purchased and where. **
- That an observation or comment can be made
on payment of a fee within 5 weeks of receipt of application by Planning
Authority. **
- Irish language newspapers must be allowed
by Planning Authorities where Gaelteacht areas are within their boundaries.
- Where the site is not in a Gaelteacht area
and the notice is in an Irish language newspaper it must also be published
in an English language newspaper from the approved list. (However, it
is not specified that it must be published in English in this instance).
** New requirements
Site Notice – Requirements
- Must be erected on site in the two week period
immediately preceding the making of an application
- Date that the site notice is erected must
be on the notice.
- Name of the Planning Authority.
- Townland name and Postal Address
- Type of permission sought
- A description of the proposed development
- If within category noted in ‘Background information’,
this must be stated.
- Application can be inspected or purchased
saying where and when (opening times of planning authority office to
be included). **
- That an observation or comment can be made
on payment of €20 within 5 weeks of receipt of application by Planning
Authority. **
- Notice must be signed by the applicant or
signature and address of agent. **
- Planning Authority may require that more
than one notice be erected. **
- Notice should be A4 in size and less than
1.5m above ground level. (If the notice is not clearly legible at A4
size it can be printed on a larger background).
- A notice relating to a second application
within 6 months of the previous one must be on a yellow background (where
the application relates to the same site or part thereof).
- Site notice must remain in place for 5 weeks
after receipt of application by Planning Authority. **
- If damaged or illegible, the notice must
be replaced. **
- Must not be concealed and located near to
the main entrance.
Content of a Planning Application
- Completed application form (where applicant
is a company, its address and registration number along with names of
directors must be given).**
- The appropriate fee
- Plans, Drawings and Maps – 6 copies of each.
o
Must be to metric scale
– Location @ 1:1250 in rural areas, 1:1000 in built-up areas, Layout @
1:500, General @ 1:200 (some require 1:100 or other as requested). [Many
areas of the country are not mapped @ 1:1250, so 1:2500 is acceptable
for these areas]
o
Site boundary in red
o
Adjacent land in applicant’s
control in blue **
o
Wayleaves in yellow
**
o
Layout to show levels
and contours **
o
Clearly distinguish
new and existing in extensions/alterations
o
Overall dimensions including
distance of structures from boundaries**
o
All maps must have OS
sheet no. and North point.
o
Name and address of
person who prepared plans
- Schedule listing the drawings (drawing 1
of 12, drawing 8 of 12 etc.). **
- The page of the newspaper containing the
notice. **
- One copy of the site notice (Location plan
must show the place on site where it is erected). **
- Where applicable a certificate under section
97 of the Act
Time Scales
- 2 weeks before application date
o
Place notice in newspaper
o
Erect site notice
- On receipt of planning application, the Authority
must make an
o
Assessment of validity
of application (no time limit, but an objective that it would be within
2 weeks of the Planning Authority receiving the application).
o
Assessment subject to
site visit
- Within 5 weeks of receipt by Planning Authority
o
Observations or submissions
by third parties
o
Site notice must stay
in place for full period
o
Decision cannot be made
by Planning Authority
- Within 8 weeks of receipt by Planning Authority
o
Decision to grant or
refuse must be reached
- Within 3 days of decision
o
PA to issue copy of
decision to applicant and those who have made submissions or observations.
- Within 4 weeks of date of decision
o
Any appeal to an Bord
Pleanala must be lodged
- Anytime during the process
o
Application may be withdrawn
by notice in writing
o
Request for further
information (see below).
o
Request for revised
plans (should be submitted within 4 weeks. If not submitted within 6 months,
the planning application is withdrawn).
Further Information Requirements
- Can be requested during decision period
- Revised plans may be requested by Planning
Authority
- Where response is ‘significant’ then
o
PA must notify all relevant
bodies
o
PA must notify all those
who submitted observations
o
PA must accept further
observations from same persons/bodies
o
No fee is payable in
respect of these second observations
o
The applicant must publish
a newspaper notice. This newspaper notice must be placed within one week
of submission of the further information. It must be headed with the name
of the Planning Authority and marked ‘Further Information’ or ‘Revised
Plans’ as appropriate and must have the name of the applicant, the address,
townland or location, the register reference number, a statement that
significant further information in relation to the application has been
lodged and that observations may be made on payment of a fee. The time
period for the submission of observations is 2 weeks from the date the
notice is published.
Duration of Permission
- Generally - 5 years
- For Outline Permission – 3 years
o
Application for Consequent
Permission must be made within 3 years
o
This period may be extended
by application
- Housing (Part V) – in some cases – 2 years
o
Applies to applications
made after 25th August 1999
o
Applies where housing
strategy not in Development Plan of the PA
o
Applies to developments
not commenced AND
o
Applies to any portion
of a commenced development where external walls have NOT been completed
- Period of validity of permission
may be extended
o
Development must have
commenced
o
Application must be
made in the last year of the validity of the application
o
Time frame required
must be reasonable
o
Why development was
not completed on time.
- An application to further extend the period
can be made and fewer particulars are required, but the applicant must
show the circumstances beyond his control that has prevented the development
being completed within the extended period of the permission.
Miscellaneous Provisions
- All documents held on Public File can be
copied
o
New Copyright and Related
Rights Act 2001
o
For information only
o
Copyright not infringed
o
Must be clearly marked
‘For Inspection Only’.
o
Declaration must be
signed by person receiving copies
- There is now formal possibility for pre-planning
consultations
- For time calculations the period 24th
Dec – 1st Jan excluded
- Where PA is inclined to grant permission
that is a material contravention of it’s own Development Plan, then
it must publish a Prescribed Notice (34-6) in an approved newspaper
Making an Appeal
o
First party, any prescribed
body
o
Those who made observations
o
Exceptionally – immediate
neighbours
o
€150 for domestic applications
o
€380 for commercial
and other applications
- Must be lodged within 4 weeks (not
one month!), of decision date of PA
- No specific requirements for type of documentation
o
Covering letter must
adequately describe the original application
Matters in Relation to Appeals
- The Bord may require revised plans
o
And may grant on the
basis of these revised plans
- All documents available for inspection
o
During the decision
period at offices of Planning Authority
o
At an Bord Pleanala
for 5 years from decision date
o
Copying as for planning
applications
o
To relevant Planning
Authority
o
To those who made observations
– by Planning Authority
o
In weekly planning list
of Planning Authority
- Submissions or Observations
o
By any party except
for referral under Section 96(5) {Social housing supply}
- Objective to make decision within 18 weeks
- The Bord may grant where development is a
material contravention of the development plan
- The Bord can dismiss vexatious, frivolous
or insubstantial appeals
- Procedures in relation to oral hearings largely
unchanged
- Remains a specialist area – seek advice and
study in detail
|