The Sustainable School Project

 

Cork School Project Energy Audit Report

Audit Date: 29 Feb 2000

Liam Mc Laughlin (‘Greening the School’ Group)

An audit of energy use in the school was carried out on the above date.

Gas (Heating)

At 0900hrs on the day of the visit, it was very cold outside. This was an ideal situation to examine the performance of the heating system.

There is good potential to reduce gas bills in the school by some minor modifications to controls and by minor changes to settings of existing controls.

Observations:

Recommendations:

  1. Set the boiler temperature to cut out at 60 deg C and to start up half an hour earlier. This may need further adjustment if these settings are a little out. This will allow more time for the further rooms to come up to temperature and minimise the cost of doing so by operating at a lower temperature.
  2. All hot water pipes in the boilerhouse should be insulated.
  3. Fit thermostatic radiator valves to the radiators in the two classrooms nearest the boilerhouse, i.e. one on each floor. These will minimise the chance of these rooms overheating if used correctly and will also significantly help in getting the other areas of the school to heat up more quickly. It may be necessary to fit thermostatic radiator valves to the next classrooms also but it would be easiest and cheapest to try them out on these two rooms first.
  4. On the day, the setting of the thermostat in the Junior Infants room was reduced. This would cause the heating pump for the ground floor to stop more quickly. This was an interim solution. Ideally this thermostat should be relocated to the coolest classroom on the circuit.
  5. On the day, the setting of the thermostat in the room above Junior Infants was increased. This allowed the hot water pump to be operated in automatic. Ideally this thermostat should also be relocated to the coolest classroom on its circuit.
  6. Once the above improvements have been implemented it would be worth looking at fitting an outside air temperature switch near the boilerhouse. This would prevent the boiler from starting on warm days and would also stop the boiler automatically earlier than the set time if the day warmed up earlier.

Based on general experience of savings typically made it should be possible to reduce natural gas consumption by at least 15% (> 1275 kWh @ 2.047p/kWh plus VAT or £26 for period 18 Nov 99 to 22 Jan 2000) in the school. If this bill were typical then annual savings would be in excess of £90. In addition to the savings, comfort levels would also increase both in the hot and cool areas of the school.

Detailed costs would need to be obtained for each of the improvements to prioritise/eliminate those that may be uneconomical.

Electricity

Uses for electricity in the school:

The ESB bill for Dec 99 / Jan 2000 was £311. The bill had an estimated reading on it but if it is representative then annual electricity usage should be approx. £1500.

There were a number of minor savings to be made, e.g. removal of redundant high energy lights outside principals office.

There is a large difference between the calculated electricity usage and the billed usage (7kW versus 15kW). This needs to be investigated to identify where the bulk of the electricity is being used and thus identify potential savings opportunities.

Electrical heating of the crèche may account for a significant amount of the ‘missing’ electrical consumption. Economical solutions may not be practical due to the condition of the building and the possibility that it may be replaced.

Recommendations:

  1. Further checking of electricity usage is required. This can be achieved by taking frequent readings of the ESB meter and logging them or by installing an electronic logger. The latter is being investigated on a loan basis.
  2. The cost/savings of replacing the current light fittings in the classrooms with more modern high efficiency fittings or tubes will be examined.
  3. Staff and students should be encouraged to switch off unnecessary lights. It is economical to switch off lights when leaving the room for periods greater than 10 minutes such as breaks.
  4. Where current switching set-up allows reduce corridor lighting to a level to permit safe access and exit via the corridors.
  5. The cost/savings of fitting automatic light switches to low occupancy areas such as toilers will be examined.

Awareness

Very high levels of awareness of the importance of minimising wastage of energy were apparent from talking to John and Ger. This was reflected in the overall approach being taken.

Recommendation:

There would be a benefit in running an energy awareness campaign as part of the ‘Greening the School’ initiative. This would help the children to become more aware of the environmental importance of energy conservation as well as helping to reduce the running costs of the school.

 

Back to the Sustainable School Project Index

 

Submissions regarding the project are most welcome. Use this link: cspadmin.ias@eircom.ie
 

 


Back to the Cork School Project homepage