|
MICROSOFT EPDC/5
In 2000, Microsoft celebrated
fifteen years of business in Ireland. In the same year, Microsoft
sited a three-acre greenfield site at the IDA South County Business
Park, Leopardstown, Co Dublin for its new European Product
Development Centre, EPDC5. This site is adjacent to the existing
EPDC/2 product development facility, which opened December 1995.
The new €42m EPDC/5 facility consists of 11,488 square meters of
floor area together with 322 car-parking spaces.
The building, designed by Gilligan Architects, comprises a
three-storey facility over basement car parking. Car parking is
also provided at ground level on a podium structure. The floor
plates are generally 50m x 50m with a 22.5m x 22.5m central atrium
area. Four no. stair/lift cores provide circulation. The basement
car parking is generally class 1 category with class 4 category
local to 3 number stair/lift core areas serving the basement. This
basement area extends beyond the building footprint under the podium
level service road and car parking areas and required a total
excavation volume of 40,000 cubic meters of which 22,000 cubic
meters was Granite rock.
A curved and inclined three-storey glazed wall provides the external
focal point at the main entrance that leads into a 510 square meter
atrium space covered entirely with roof glazing. Aluminium framed
glazing/cladding covers the major area of external elevations and
the remaining core elevations are finished in limestone cladding.
The building was initially planned as a development/investment
opportunity with fixed lease agreements to Microsoft. However due
to marketplace conditions, Microsoft negotiated a contract with
building contractors, G & T Crampton Ltd.
Various structural schemes were proposed including a concrete flat
slab structure. However, based on programming requirements, the
chosen scheme was a steel framed three-storey building set out on a
7.5m x 7.5m grid layout. UC sections were used for column and the
floor structures comprised a 335mm deep composite concrete slab on
SD 225 decking which in turn is supported on ASB beam sections. To
accommodate the higher loading of the ground floor to the atrium a
300mm deep flat slab structure was provided. A flat slab structure
on concrete columns provides for the podium areas and all core walls
are formed with insitu concrete.
Initially it was intended to provide expansion joints through the
building but on review of core locations, it was decided to engineer
out building movements utilising the 4 no. perimeter cores and by
providing UC steel tie beam sections between columns at floor plate
levels. A total of 700 tonnes of hot rolled steel sections together
with 40,000 cubic meters of concrete make up the structural frame.
Lateral stability is achieved via floor plate action through to the
4 no. concrete core structures. Steel members supporting the glass
atrium roof and inclined/covered glazed entrance facade comprises
CHS sections of various dimensions connected by steel side plates to
form unique tapered elliptical profiles.
Substantial geotechnical investigations were initiated at early
stages to establish rock contour levels. In general, granite rock
was found to underlie approximately 600mm of topsoil/gravely clay.
As a result, conventional pad/strip footings were used as
foundations. These were designed to be integral with the basement
concrete slab.
In September 2001 G & T Crampton Ltd commenced on a 19-month
construction programme broken into two stages i.e. (1) Shell &
Core (2) Fitout. In July 2003, Microsoft Ireland gained
possession of its new EPDC/5 facility on time and on budget.
Joe
Ryan, Hanley Pepper
|