Workshop
Build
|
|||
1 - The Plan | 2 - Foundations | 3 - Rising Walls | 4 - Underfloor Insulation |
5 - Underfloor Pipes Heating In | 6 - Concrete Slab Poured | 7 - Timber Frame Erected | 8 - View From Store Where Everything Else Goes |
9 - Slates, Windows & Doors In | 10 - View From The Other Side | 11 - Insulated Garage Door Closeup | 12 - 110mm Duct Replaced With 160mm |
13 - Damage To underfloor Heating Pipe After Replacing Duct | 14 - 160mm Duct Concreted In | 15 - The Blockwork Is Started Finally | 16 - Blockwork Finished |
17 - Plastering Complete Near Side | 18 - Plastering Complete Far Side | 19 - The Plastering Product Used - Colour Sand | 20 - The First Fix Wiring Started But Only Just |
21 - The Cyclone Arrives On Site - Not Yet Assembled | 22 - The 12mm Ply Arrives For Sheeting The Walls | 23 - And The First On The Back Wall | 24 - The Ceilings Plastered |
25 - Time To Start Assembling The Cyclone - First the Filters | 26 - What they Look Like Together | 27 - Now For The Cyclone Itself - Vortex Pipe & Upper Cyclone Body | 28 - The Vortex Pipe Bolted Into The Upper Cyclone Body |
29 - The Motor Blower | 30 - The Motor Blower Bolted To The Upper Cyclone Body | 31 - The Cyclone In Its Final Home | |